Daily Reports
Site engineer daily progress reports across all projects.
Report Log
Showing 5 of 38 reports| PROJECT | EST. HOURS | LOGGED HRS | ACCURACY | START DATE | DUE DATE | USERS | PROGRESS | STATUS | |
|---|---|---|---|---|---|---|---|---|---|
Riverdale Commercial Tower Foundation waterproofing B2 |
48h | 46h | 95.8% | Jun 10 | Jun 20 | RS
PM
|
85% |
On Track | |
NH-48 Highway Widening Asphalt laying — Km 34–38 |
72h | 61h | 84.7% | Jun 8 | Jun 22 | AP
KN
|
58% |
Delayed | |
Greenview Residential Phase 2 Floor 7 plastering & MEP |
60h | 58h | 96.7% | Jun 12 | Jun 24 | RS
VT
NG
|
92% |
On Track | |
Metro Station Refurbishment Snag list closure & handover |
32h | 32h | 100% | Jun 1 | Jun 15 | SD
MK
|
100% |
Completed | |
Industrial Warehouse Sector 9 Steel truss & loading bay |
96h | 52h | 54.2% | Jun 5 | Jul 10 | KN
AP
|
42% |
Delayed |