Riverdale Commercial Tower
Welcome back, Admin — site-specific performance dashboard.
+2.4% this week
72%
Overall Progress (On Track)
94% Attendance
98
Labor & Staff on Site Today
1 Active Pour
50%
Active Checklists Completion
4 bills pending
₹98.4L
Unpaid Site Invoices
Project Milestones & Schedule
72% Completed| MILESTONE PHASE | TARGET DATE | WEIGHT | PROGRESS | STATUS |
|---|---|---|---|---|
| Foundation & Piling | 30 Oct 2025 | 15% |
100%
|
Completed |
| Substructure & Basements | 15 Jan 2026 | 15% |
100%
|
Completed |
| Superstructure (Floors 1-12) | 10 Apr 2026 | 25% |
100%
|
Completed |
| Superstructure (Floors 13-24) | 15 Aug 2026 | 20% |
75%
|
On Track |
| MEP & Plumbing Installation | 30 Sep 2026 | 10% |
42%
|
On Track |
| Facade Glazing & Masonry | 15 Nov 2026 | 10% |
15%
|
Delayed |
| Finishing & Handover | 31 Jan 2027 | 5% |
0%
|
Pending |
Recent Site Activity Logs
View Reports →Foundation waterproofing B2 completed
Verified
Ravi Shankar logged and completed 46h out of 48h estimated with 95.8% accuracy. Approved by PM.
Today, 9:45 AM
Weekly Safety Audit checklist started
In Progress
Safety engineer initiated PPE compliance checks and scaffolding tags inspection.
Today, 8:15 AM
Late Check-ins reported
Notice
31 workers flagged with late entry for the morning shift. Average delay is 22 minutes.
Today, 8:00 AM
Concrete slump test rejected
Critical
Batch #3 transit mixer from UltraTech rejected due to workability issues (slump value 60mm vs target 120mm).
Yesterday, 4:30 PM
Active Checklists
View All →
Foundation Pour · B2 Slab
3 / 6 Done
Rebar inspection signed off
Formwork alignment verified
Concrete mix design approved
Slump test — sample 1 (Active)
Safety Audit — Weekly
2 / 5 Done
PPE compliance check
Fire extinguisher inspection
Scaffolding tag review (Active)
Alerts & Reminders
4Trade License Expiry
CriticalExpires in 4 days — Renew immediately
Jun 18, 2026
PO Approval Pending
Warning3 purchase orders awaiting approval
2 hours ago
Invoice Overdue
WarningInvoice #INV-2041 overdue by 7 days
Jun 15, 2026
Insurance Certificate
CriticalExpires in 9 days — Upload renewal docs
Jun 23, 2026